The Physics Derivation Graph relies on a diverse set of skills. To speed up the development process we could identify separable tasks and then spread the tasks among a team of contributors. Collaboration requires coordination, and that coordination can be top-down or organic or a mixture.
This post focuses on the top-down approach and assumes an omniscient view.
A standard data structure in project management is the Gantt chart. A Gantt chart uses information about tasks, task dependencies, task durations, and dates to create a visualization associated with a project.
| task ID | task description | task duration [days] | depends on tasks | earliest start date |
|---|---|---|---|---|
| 14235 | something useful | 3 | N/A | 2022-03-01 |
| 25532 | hard work | 2 | [14235] | N/A |
| 3456252 | keeping busy | 3 | [25532] | N/A |
That table can be visualized with tasks versus time:
![]() |
| Visualization of a Gantt chart. Four tasks. Task 2 and 3 depend on task 1 being completed. Task 4 depends on task 2 being completed. |
That data structure doesn't account for staffing, skills, equipment, or budget. The Gantt chart doesn't account for uncertainty of task duration, nor alternative paths.
Project management involves contingency planning.
IF this THEN that ELSE other
Every conditional statement is a branching of possible paths, each a separate Gantt chart.
A single Gantt chart is a snapshot of a single path.
| task ID | task description | task duration [days] | depends on tasks | earliest start date | depends on equipment | minimum skill set and level | uncertainty in duration [days] |
|---|---|---|---|---|---|---|---|
| 14235 | something useful | 3 | N/A | 2022-03-01 | [Photoshop] | photo editing, intermediate | +/-1 |
| 25532 | hard work | 2 | [14235] | N/A | [Excel] | math, beginner; text editing, beginner | +2 |
| 3456252 | keeping busy | 3 | [25532] | N/A | Chrome browser | clicking on links, beginner | 0 |
That information needs to be augmented with a cost table for equipment:
| equipment | cost per day [USD] | acquisition cost [USD] |
|---|---|---|
| Photoshop | 0 | 100 |
| Excel | 0 | 20 |
| Chrome browser | 0 | 0 |
Lastly, we need people who can do the tasks.
| person name | hourly cost [USD] | skill and level | dates available |
|---|---|---|---|
| Alice | 20 | Excel, beginner; text editing, intermediate | [2022-01-02, 2022-01-03, 2022-01-04] |
| Bob | 15 | Excel, intermediate; Math, beginner | [2022-02-01, 2022-02-15, 2022-02-24] |
| Charlie | 24 | photo editing, beginner | [2022-01-12, 2022-01-23, 2022-01-24] |
Even though the issue can be formulated into a set of data structures
Blockers are the amount of time needed to
Blockers that aren't time-based:
The top-down omniscient view of project management is an unrealistic fantasy. However, it might be a helpful artifact for negotiation among decision makers. The alternative (where decision makers don't have a quantitative model to argue about) devolves into reliance on personal relationships, turf battles, and political factions. Bureaucratic processes evolve as a substitute for the lack of top-down omniscient view of project management.